Atlantic Street Bridge

The Atlantic Street Bridge will soon begin its journey to replace the existing bridge that was built more than a century ago. The new bridge is expected to be rolled into place during a nine-day period from June 28 through July 8, with intermittent local road closures and detours.
Description

The Challenge, The Solution, The Results

Customer

Awards

Project Size

Steel: 4500 tons | HDG: 4500 tons

Components

Piling, Bridge beams, plate girders, bridge accessories.

The Atlantic Street Bridge will soon begin its journey to replace the existing bridge that was built more than a century ago. The new bridge is expected to be rolled into place during a nine-day period from June 28 through July 8, with intermittent local road closures and detours. With traditional construction, an undertaking of this magnitude would typically take years to complete.

Commuters could expect major train disruption, and access beneath the bridge would be closed for the entire duration of the project. Accelerated Bridge Construction (ABC) minimizes such inconveniences to months and, in some cases, days. Pedestrians and those traveling in the Stamford area have seen the new bridge taking shape in two off-site construction areas near the job site—one near Elm Street and the other adjacent to the existing bridge on Atlantic Street.

For the replacement of the Atlantic Street Bridge, long-term closures of the underpass were only required to widen and lower the roadway. At the Elm Street site, temporary concrete foundations will accommodate the assembly of the bridge superstructure decks. The massive steel girders (88 total) weighing approximately 38,500 pounds each after galvanizing.

The girders were originally specified to be metallized, as the owner was not aware that girders of this size and weight were able to be hot-dip galvanized. The change over to galvanizing allowed the project to be completed faster and at a lower budget than originally planned. Once the concrete was placed over the massive steel girders, each 70-foot span weighed in at approximately 3.8 million pounds.

Once the concrete cured, the forms removed and the spans readied for transport to the job site. Special self-propelled modular transporters used hydraulic power to raise the bridge spans off the temporary foundations and move them, span by span, into place. Construction crews worked 24/7 to demolish the existing bridge in stages and replaced the old with the new.

In this way, two tracks remained active and rail service was operational under a special schedule. Thanks to the ability of hot-dip galvanizing to expedite the overall project schedule, the project concluded on time and without track interruption.

Gallery

Every Detail Tells Our Story

Dive deeper into this project with exclusive images that capture the craftsmanship, precision, and galvanizing expertise that brought this vision to life.

No items found.
Our Portfolio

Protecting America's Infrastructure One Dip at a Time

Liberty Place Parking Garage

The developer of the new Liberty Place Apartments in the heart of Columbus, Ohios Brewery district was seeking an economical, long lasting solution for the parking problem surrounding their project.

Fifth Third Ballpark

Fifth Third Ballpark is the largest outdoor entertainment venue in Western Michigan. It offers family recreation and entertainment all in one venue!

Pyrmont Road Bridge Rehab

Built in 1904, this bridge is a beautiful nine-panel pin-connected Camelback truss bridge. Pin-connected Camelback truss bridges are uncommon, far less common than Parker trusses of their time.

Markwest Energy Seneca Processing Facility

The fully integrated midstream system in the Utica shale processing facility built for Markwest Energy will require a durable coating system that withstands the test of time in a harsh, corrosive environment.

Ready to Transform Your Project with Industry-Leading Galvanizing?

Don't let corrosion compromise your investment. Partner with V&S Galvanizing for proven protection that outlasts the competition. Our expert team delivers custom solutions, rapid turnaround, and nationwide reliability that keeps your project on schedule and on budget.

Hot dip galvanizing steel